CSC 308 Milestone 3
CSC 308 Milestone 3
Due: Fourth week. (Initial review at team lab meeting;
completed milestone checked into project directory by Friday, 7PM.)
Activities
Your work for Milestone 3 involves continuation of the work begun in Milestone
2, plus administrative activities. The specific tasks are:
-
Continue to refine and add new functional requirements scenarios to Section 2.
-
Refine the individual work assignments for each team member's contributions to
Section 2 of the requirements specification. Record these assignments in the
work-breakdown.html file in the project administration
directory.
-
Assign inspection test duties for Weeks 4 - 11 1.
Record these duties in the file administration/inspection-roster.html,
in a table of the following form:
| Week No.
| Team Member
| Initials
|
| 4
| member a
|
|
| 5
| member b
|
|
| 6
| member c
|
|
| 7
| member d
|
|
| 8
| member e
|
|
| 9
| member f
|
|
| 11
| member g
|
|
There are additional instructions for filling in this table in the
SOP on requirements testing.