2.3.5 P1 JGP 4mar15 FIX Replace "you" with "the user" or something similar.
2.3.5 I1 JGP 4mar15 FIX Not easy to see where the "Student" menu that needs to be clicked is.
2.3.5 I1 JGP 4mar15 FIX Pie chart should be empty
2.3.5 P2 JGP 4mar15 FIX Replace "you" with "the user" or something similar.
2.3.5 I2 JGP 4mar15 FIX Not easy to see where the "Student" menu command that needs to be clicked is.
2.3.5 I2 JGP 4mar15 FIX Pie chart should be empty
2.3.5 P3 JGP 4mar15 DONE
2.3.5 I3 JGP 4mar15 DONE
2.3.5 P4 JGP 4mar15 DONE