Inspection Report
Component | Inspector | Date | Status | Remarks |
2.5 | MFR | 23Nov09 | DONE | |
2.5 P1 | MFR | 23Nov09 | FIX | needs to need |
2.5 I1 | MFR | 23Nov09 | DONE | |
2.5 I2 | MFR | 23Nov09 | DONE | |
2.5 P2 | MFR | 23Nov09 | FIX | opened to opens |
2.5 I3 | MFR | 23Nov09 | FIX | remove the toolbar and add the tabs we have in the main UI |
2.5 P3 | MFR | 23Nov09 | DONE | |
2.5 P4 | MFR | 23Nov09 | FIX | "...Figure 3 all...completed." to "...Figure 3 the instructor completes all grading operations.", can click to clicks |
2.5 P5 | MFR | 23Nov09 | DONE | |
2.5 P6 | MFR | 23Nov09 | FIX | it to TestTool, was to is, can go in and mark to goes in and marks, will change to changes |
2.5 P7 | MFR | 23Nov09 | FIX | can click to clicks, "This will make...column" to "This marks the current student's test as graded by highlighting their name in green in the student column" |
2.5 A1 | MFR | 23Nov09 | DONE | |
2.5 A2 | MFR | 23Nov09 | DONE | |
2.5 A3 | MFR | 23Nov09 | FIX | 'up' should link to functional.html |
2.5 A4 | MFR | 23Nov09 | DONE |