Inspection Test of Phase 3 Longform Requirements
Component | Inspector | Date | Status | Remarks |
2.1.1 | TY | 11/19/2011 | Done | Login screen shouldn't have hilton already logged in. |
2.2.1P1 | TY | 11/19/2011 | Fix | Include in the description what the +2's indicate in the Auto-Generate Courses list. |
2.2.1I3 | TY | 11/19/2011 | Fix | Styling on cells needs to be improved for clarity. |
2.2.2P1 | TY | 11/19/2011 | Fix | The user can only drag a course onto one day column at a time, how do they specify which days the course should appear on? i.e. if the user drags a course on to the Monday column, how does the program know if they want to schedule the course for MWF, MTWR, MF ...etc? |
2.2.2P2 | TY | 11/19/2011 | Fix | Showing a radio box with an option for each possible permutation of days might not scale well when many permutations are possible. Consider a course that is dragged onto Monday, possible permutations are M, MT, MW, MR, MF, MTW, MTR, MTF, MWR, MWF, MRF, MTWR, MTWF, MTRF, MWRF, MTWRF. |
2.2.2I2 | TY | 11/19/2011 | Fix | Image shows that the course is being scheduled from 7AM-9PM, looks like it should be 9AM. |
2.2.2 | TY | 11/19/2011 | Fix | In all the images which show a brightly colored schedule item, it's hard to tell that these items are in the middle of a drag; Add a mouse pointer over the schedule items to indicate that they are being dragged. |