Inspection Test of Phase 1 Release



Individual Slide Inspections:

Component Inspector Date Status Remarks
2.1P1 MJS 29oct11 DONE  
2.1.1 MJS 29oct11 FIX The banner isn't really a placeholder. It is a reminder of the program that is being used. Every site keeps a part of it that reminds the user they are using their site.
2.1.1I1 MJS 29oct11 DONE  
2.1.1P2 MJS 29oct11 DONE  
2.1.1I2 MJS 29oct11 DONE  
2.1.1P3 MJS 29oct11 DONE  
2.1.1I3 MJS 29oct11 DONE  
2.1.2P1 MJS 29oct11 DONE  
2.1.2I1 MJS 29oct11 DONE  
2.1.2P2 MJS 29oct11 DONE  
2.1.2I2 MJS 29oct11 DONE  
2.1.3P1 MJS 29oct11 DONE  
2.1.3I1 MJS 29oct11 DONE  
2.1.3P2 MJS 29oct11 DONE  
Overall, the page needs to be reworded into present tense and use active voice. All paragraphs marked with DONE still need to be reworked in this sense.