This week |
Last week |
Weeks on List |
Risk (priority) |
Risk resolution progress |
1 |
1 |
5 |
Creeping requirements (120) |
|
2 |
5 |
5 |
Requirements or
developer gold-plating (190) |
|
3 |
2 |
4 |
Released software has
low quality (230) |
|
4 |
7 |
5 |
Unachievable schedule (280) |
|
5 |
4 |
2 |
Unstable tools delay
schedule (390) |
|
6 |
- |
1 |
High turnover (420) |
|
7 |
3 |
5 |
Friction between
developers and customers (480) |
|
8 |
6 |
5 |
Unproductive office space (645) |
|
Weeks on List |
Date Retired |
Risk | Risk Resolution |
2 |
1/20/03 |
Backup of Files | The team has decided to have the whole project backed up by the CVS administrator every Friday so that the project files would be at most one week old if file loss occurs. In addition, it's advised that all team members should also back up their own work daily. |
4 |
2/03/03 |
Power Outage | Team members will take extra precautions when working on their individual assignments. |
5 |
2/03/03 |
Quality Assurance | All team members are expected to refer to the SQAP for references on what to do for their particular assignments and how to do them. Various guidelines have been created for individual tasks to ensure utmost quality. |
3 |
2/03/03 |
Log Books | It has become apparent that all team members are turning in their log books on time and correctly; Therefore, this risk has been resolved. |
5 |
2/03/03 |
Rapid changes in Requirements | Our "plan of attack" was indeed improved so we do not need to perform any major revisions to our software development process and schedule. |
Date |
Author |
Description |
This material is copied and/or adapted from the Survival Guide Website at www.construx.com/survivalguide/. This material is copyright © 1993-1998 Steven C. McConnell. Permission is hereby given to copy, adapt, and distribute this material as long as this notice is included on all such materials and the materials are not sold, licensed, or otherwise distributed for commercial gain.