Fetter has established the following formal criteria that must be met before the software can be released.
Release 2 Release Criteria Calculations
1. Complete - We have completed more than the planned amount (actual: 1673, planned: 1565).
2. Complete - During this release, there have been 359 lines of code added. The number of lines added during the week prior to the release totals 127. 127 / 359 = 35%
3. Complete - 100% of our binary miniature milesontes have been completed (for more information view our Integration Plan).
4. Complete - There are no severity 1 open defects. (for more information view our current defect list)
5. Complete - We have reported 36 defects and we predicted (by using the assigned prediction method) 36. Thus, we have reported 100% of predicted. (I know this seems a little fortuitous, but it's because our planned lines of code is about 100 less than our actual lines of code. If I predicted our defects using our actual lines of code, it would be 41 defects. For more information look at our visibility calculations page.)
6. Complete - We have reported 9 severity 2 defects. Of those 9, 7 have been fixed, which is 78%.
7. Complete - In the four days prior to release, 3 defects have been reported while 24 have been fixed. The ratio of defects reported to defects fixed is 13%.
8. Complete - The Release Sign-Off form has been signed by all parties.
Last updated on 03-08-01 by Michael Hebron
First Draft created on 02-03-01 by Phillip Hansen