Stage 2
Milestones |
Dates |
Completed? |
|
Requirements
update |
1/17/2002 |
Yes |
|
Staged
Delivery Plan written |
1/17/2002 |
Yes |
|
Project
Plan Updated |
1/17/2002 |
Yes |
|
Build
Instructions written |
1/22/2002 |
Yes |
|
Quality
Assurance Plan Updated |
1/17/2002 |
Yes |
|
Process Definitions
written (Refer to web page template) |
Instructor defined, see his
schedule |
Yes |
|
Detailed
Design updated |
1/22/2002 |
Yes |
|
Test
Cases written |
1/31/2002 |
Yes |
|
Source
Code written and updated for Stage 2 |
1/31/2002 |
Yes |
|
Source Code
integrated completely for Stage 2 |
2/2/2002 |
Yes |
|
Program
submitted for Acceptance Testing |
2/7/2002 |
Yes |
|
Program
submitted to Instructor |
2/12/2002 |
Yes |
|
Designer/Instructor
Meeting |
2/13/2002 |
Yes |
|
|
|
|
|
Stage 3
Milestones |
|
|
|
Requirements
Update |
2/19/2002 |
Yes |
|
Project
Plan Updated |
2/20/2002 |
Yes |
|
Quality
Assurance Plan Updated |
2/21/2002 |
Yes |
|
Recalibration
for Stage 3 |
2/24/2002 |
Yes |
|
Coding
for Stage 3 |
2/26/2002 - 3/5/2002 |
Yes |
|
Customer
Meeting |
2/26/2002 |
Yes |
|
Writing
Test Cases for Stage 3 |
2/26/2002 – 3/7/2002 |
Yes |
|
Customer
Meeting |
2/28/2002 |
Yes |
|
Customer
Meeting |
3/5/2002 |
No |
|
Source
Code integrated completely for Stage 3 |
3/7/2002 |
Yes |
|
System
Testing for Stage 3 |
3/7/2002 – 3/12/2002 |
Yes |
|
User
Manual written (SRS) |
3/11/2002 |
Yes |
|
All
tracking/process documents updated |
3/11/2002 |
Yes |
|
All
Defects Removed |
3/11/2002 |
Yes |
|
Program
submitted for Final Acceptance |
3/12/2002 |
Yes |
|
Date |
Author |
Change |
|
3/10 |
S. Pinto |
Updated for Stage 3 with updated dates |
|
2/25 |
S. Pinto |
Updated for Stage 3 with initial estimates |
|
2/11 |
K. Blomseth |
Corrected errors |
|
2/04 |
K. Blomseth |
Updated Schedule |
|
1/18 |
K. Blomseth |
Initial Posting |