PSP Project Summary
Programmer ___________________________
Program ___________________________
Date ______________
Time in Phase
Phase
|
Minutes
|
% of Total
|
Design
|
|
|
Code
|
|
|
Compile
|
|
|
Test
|
|
|
Total
|
|
|
Defects Injected
Phase
|
Number
|
% of Total
|
Design
|
|
|
Code
|
|
|
Compile
|
|
|
Test
|
|
|
Total
|
|
|
Summary
Program Size ______________ lines
of code (LOC).
Determine using the Lines of Code
counting tool.
Productivity (Calculated) ______________ LOC / hr.
(Compute as Size/Total Time*60)
Defect Rate (Calculated) ______________ Defects /
KLOC.