| CSC/CPE406 Software Deployment Tentative Schedule | ||||||
| Date | Week | Lecture Topic | Reading To Be Completed | Individual Deliverables | Team Deliverables | |
| 3/29/2010 | 1 | Introductions, syllabus, Iteration 5 deliverables | ||||
| 3/31/2010 | 1 | Cesar Chavez Holiday - no classes | ||||
| 4/3/2009 | 1 | Software Quality Assurance | WELC:Foreward-Ch.2 | Iteration 5 task list, estimates, and assignments | ||
| 4/5/2010 | 2 | Team Meetings (Dr. Janzen at conference) | ||||
| 4/7/2010 | 2 | Team Meetings (Dr. Janzen at conference) | WELC:Ch.3-5 | |||
| 4/9/2010 | 2 | Team Meetings (Dr. Janzen at conference) | SVN Book Ch. 4 | |||
| 4/12/2010 | 3 | Furlough | ||||
| 4/14/2010 | 3 | Deploy Version 1 to each other | Status Report | |||
| 4/16/2010 | 3 | Customer Meeting: Planning Game for Iteration 6 new features | Iteration 5, Deploy Version 1 to Customer | |||
| 4/19/2010 | 4 | Working Effectively with Legacy Code: | WELC:Ch.6-7,p.323-344 | Iteration 6 task list, estimates, and assignments | ||
| 4/21/2010 | 4 | Working Effectively with Legacy Code: | WELC:Ch.8-9,p.345-351 | It. 5 Time, Self/Peer Evaluation, ICST in SEEDS | ||
| 4/23/2010 | 4 | Project Review | ||||
| 4/26/2010 | 5 | Working Effectively with Legacy Code: | WELC:Ch.10-11,p.352-378 | |||
| 4/28/2010 | 5 | Working Effectively with Legacy Code:, System Integration | WELC:Ch.12-13,p.379-391 | Status Report | ||
| 4/30/2010 | 5 | Customer Meeting: Planning Game for Iteration 7 new features | Iteration 6 | |||
| 5/3/2010 | 6 | Midterm Exam | Iteration 7 task list, estimates, and assignments | |||
| 5/5/2010 | 6 | Furlough | It. 6 Time | |||
| 5/7/2010 | 6 | Project Review | ||||
| 5/10/2010 | 7 | Working Effectively with Legacy Code: | WELC:Ch.14-17,p.392-398 | |||
| 5/12/2010 | 7 | Working Effectively with Legacy Code: | WELC:Ch.18-20,p.399-403 | Status Report | ||
| 5/14/2010 | 7 | Customer Meeting: Planning Game for Iteration 8 new features | Iteration 7 | |||
| 5/17/2010 | 8 | Working Effectively with Legacy Code: | WELC:Ch.21-24,p.404-414 | Iteration 8 task list, estimates, and assignments | ||
| 5/19/2010 | 8 | Google I/O | It. 7 Time | |||
| 5/21/2010 | 8 | IAB Presentations | ||||
| 5/24/2010 | 9 | Furlough | ||||
| 5/26/2010 | 9 | Software marketing, licensing, and vendor issues | New Times Article | Status Report | ||
| 5/28/2010 | 9 | Midterm Exam | Guest Speaker Reports | |||
| 5/31/2010 | 10 | Memorial Day Holiday - no classes | ||||
| 6/2/2010 | 10 | Practice Presentation, course evaluations | It. 8 Time, Self/Peer Evaluation | Iteration 8, Deploy Version 2 to Customer | ||
| 6/4/2010 | 10 | Project Presentation | ||||
| 6/7/2010 | Retrospective 10:10am-1pm | |||||