09/21 Week 1, Lab 2

Accomplishments:

Formed Team and gave ourselves a name, logo, and motto.

Determined when we were unavailable to meet and assigned job positions. (Excel Documentation).

Assignments:

Tony T: Initial web page design assigned to Tony T.

Ben: create team member’s nametags.

Susan: Meeting documentation

09/26 Week 2, Lab 3

Chris Tardy

Accomplishments:

Web page in progress

Nametags completed

Team meetings schedule: indicates free times when all members can meet

Assignments:

Tony T: Complete initial web page

Susan: email meeting schedule to group

Susan: complete draft project plan and send to Tony T

09/28 Week 2, Lab 4

Meeting with customer. Discussed requirements of project.

FORMAL GROUP MEETING

Accomplishments:

Current working links include:

Team photo (drop down menu, link team photo)

Draft Project Plan (link planning)

Links in progress include:

Team roster

Contact information

Planning pages

Tracking pages

Deliverables pages

  • Draft Project Plan: included team member information in PROJECT TEAM section, filled out TEAM ORGANIZATION information with team members names and saved changes to word document for further revision

Unfinished Tasks:

    • None at this time

Problems Encountered:

    • None at this time

Assigned Tasks:

    • None at this time

WORKING MEETING:

More information is needed on specifications. Questions still present. Discussed project scope.

 

10/3 Week 3, Lab 5

FORMAL MEETING:

Accomplishments:

none

Unfinished Tasks:

web pages for: draft project schedule, team journal, and the contact us

Some changes may need to be made as far as the organization links

Problems Encountered:

Not prepared

Assigned Tasks:

Group meeting Wednesday 10/4 at 8:30pm, Chris’s work on California St

Tony will bring Dream Weaver program to meeting to facilitate web update

 

WORKING MEETING NOTES

WHAT FUNCTIONS NEED TO BE PERFORMED?

display resource bundle(s) (show 2 bundles next to each other?)

Adding keys to root: function/modify keys

display all keys in root, (show differences between parent and child?)

import or make new resource bundle -- four possible file formats: java source + 3 more

project file: containing a list of resource bundles saved to hard drive

 

UI SO FAR:

show tree of all resource bundles and hierarchy

three columns, from left to right: key, key value, comments

FILE

New

New Project

New Child

Save All

Save As

EDIT

undo

cut

paste

new key

delete key

modify key

modify value

TOOLS

preferences

tests

number

message

choice

HELP

 

 

 

| home | team | planning | tracking | technical | deliverables | contact |

Copyright (c) 2000 QuartzWare. All rights reserved.
Site created by Anthony Tomarchio of Teknokratz, Inc.